Client: Havant Council

Duration: Various dates over the last 18 years 

Contract Description

Beach Recyling along Hayling Island Seafront.

Shingle is excavated using 52t excavator and transported along to the groynes in 40ton dumptrucks, then the dozer levels the shingle in the groynes.

6-8 dumptrucks are used to maximise the material moved in a short window of time.